Construction Update: Pettibone Rd 10.4

  • Posted on Sun 4, October 2009

Start of Phase 3 Work

Beginning Monday, October 5, Pettibone Rd Phase 3 construction is scheduled to start. Phase 3 is the section of Pettibone Rd from the western city line to SOM Center Rd.

Weather permitting, Kenmore Construction will be installing temporary pavement on the north side of Phase 3 Pettibone Road beginning at the west county line and working east to SOM Center Rd. This activity will take approximately 12 working days.

Two way traffic will be maintained in Phase 3, watch for construction personnel directing traffic.

Phase 1 Paving

Beginning Monday, October 5, Pettibone Rd Phase 1 final paving is scheduled to start. Phase 1 is the section of Pettibone Rd from Liberty Rd to the eastern city line.

Weather permitting, Kenmore Construction will be installing asphalt pavement for approximately 3 working days. After the pavement is is installed traffic markings will be painted on the road.

The scheduled date for opening Pettibone Rd Phase 1 to two way traffice is October 12, weather permitting.