An update from www.solonohio.org on Pettibone Rd. construction
The Contractor is currently performing the cement stabilization
process between Liberty Rd. and Aurora Rd., on the north side. We anticipate that this work will be completed by the end of the day, Monday, August 10, 2009, weather permitting. Please be advised that there is a seven day cure period following this process, when the Contractor will be unable to drive on the sub-grade. During the cure period, while it may appear as though no work is being performed in front of your property, the Contractor will be performing other items of work in various locations.
Additionally, asphalt paving will continue through Monday, August 10, 2009, east of Aurora Rd., on the north side. This work will be followed by grading, topsoil, and seeding, behind the curb. We anticipate that two-way traffic may be restored, in this area, as early as September 1, 1009, weather permitting.